Dept. of Trans. PROGRESS Serial No. Contract No. 14-234-08-23 02-4G1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 47% 02-TEH-32-10.0/16.0 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-14 DIG IT CONSTRUCTION INC PO BOX 494 CHESTER CA 96020 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 207,934.81 207,934.81 2.a. Extra Work 19,619.78 19,619.78 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 227,554.59 227,554.59 5. Mobilization 6. Total Work Completed 227,554.59 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 227,554.59 227,554.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 227,554.59