Dept. of Trans. PROGRESS Serial No. Contract No. 18-117-10-05 02-4G2404 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 4% Location: Federal Project: 02-SIS-5-R25.2/R25.2 ACIM-005-9(178) Progress payment No. 001 Payment period ending: 04-20-18 J F SHEA CONSTRUCTION INC PO BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 222,112.00 222,112.00 2. a. Extra Work 13,620.67 13,620.67 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 235,732.67 235,732.67 5. Mobilization 200,000.00 200,000.00 6. Total Work Completed 435,732.67 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 435,732.67 435,732.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 435,732.67