Dept. of Trans. PROGRESS Serial No. Contract No. 18-207-12-00 02-4G2504 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 35% Location: Federal Project: 02-TRI-3-32.8/39.8 ACST-P003(35) Progress payment No. 002 Payment period ending: 07-20-18 R BROWN CONSTRUCTION CO INC PO BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 368,277.93 352,777.93 2. a. Extra Work 20,005.60 11,031.80 b. Adustment Comp. 3. Materials on Hand 117,997.35 117,997.35 4. Earned Subject to Retention 506,280.88 481,807.08 5. Mobilization 190,000.00 190,000.00 6. Total Work Completed 578,283.53 7. Deductions -1,962.15 -1,962.15 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 694,318.73 669,844.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 669,844.93