Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-340-10-28 02-4G2504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-TRI-3-32.8/39.8 ACST-P003(35) Progress payment No. 006 Payment period ending: 10-31-18 R BROWN CONSTRUCTION CO INC PO BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,712,685.48 53,335.78 2. a. Extra Work 79,565.71 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,792,251.19 53,335.78 5. Mobilization 200,000.00 0.00 6. Total Work Completed 1,992,251.19 7. Deductions 0.00 2,065.43 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,992,251.19 55,401.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 55,401.21