Dept. of Trans. PROGRESS Serial No. Contract No. 20-086-10-35 02-4G41U4 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 0% Location: Federal Project: 02-SHA-5-56.6/67.0 B1IM-005-8(362) Progress payment No. 002 Payment period ending: 03-20-20 J F SHEA CONSTRUCTION INC PO BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 222,717.45 103,811.20 2. a. Extra Work 7,404.42 7,404.42 b. Adustment Comp. 3. Materials on Hand 34,506.00 34,506.00 4. Earned Subject to Retention 264,627.87 145,721.62 5. Mobilization 6. Total Work Completed 230,121.87 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 264,627.87 145,721.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 145,721.62