Dept. of Trans. PROGRESS Serial No. Contract No. 21-146-12-07 02-4G4404 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 4% Location: Federal Project: 02-SIS-3-38.0/38.6 NONE Progress payment No. 001 Payment period ending: 05-20-21 STEELHEAD CONSTRUCTORS JV PO BOX 536 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 97,240.00 97,240.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 97,240.00 97,240.00 5. Mobilization 6. Total Work Completed 97,240.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 97,240.00 97,240.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 97,240.00