Dept. of Trans. PROGRESS Serial No. Contract No. 15-112-10-51 02-4G4804 PROGRESS PAYMENT VOUCHER %complete: %time: 15% 9% Location: Federal Project: 02-SHA-299-18.4/18.7 NHP-P299(186) Progress payment No. 002 Payment period ending: 04-20-15 RTA CONSTRUCTION, INC. 9614 TANQUERAY COURT REDDING CA 96003 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 261,451.28 127,232.22 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 261,451.28 127,232.22 5. Mobilization 15,000.00 5,000.00 6. Total Work Completed 276,451.28 7. Deductions -6,000.00 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 270,451.28 126,232.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 126,232.22