Dept. of Trans. PROGRESS Serial No. Contract No. 21-328-13-58 02-4G5304 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 89% Location: Federal Project: 02-TRI-299 NONE Progress payment No. 006 Payment period ending: 11-20-21 SERAFIX ENGINEERING CONTRACTORS INC 7 CROW CANYON CT #250 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,678,195.60 457,043.00 2. a. Extra Work 33,479.57 0.00 b. Adustment Comp. -800.00 -800.00 3. Materials on Hand 4. Earned Subject to Retention 1,710,875.17 456,243.00 5. Mobilization 188,000.00 0.00 6. Total Work Completed 1,898,875.17 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,888,875.17 446,243.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 446,243.00