Dept. of Trans. PROGRESS Serial No. Contract No. 18-296-15-23 02-4G5504 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 34% Location: Federal Project: 02-SIS-5-2.7/R11.4 ACIM-005-9(177) Progress payment No. 005 Payment period ending: 10-20-18 J F SHEA CONSTRUCTION INC PO BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,305,253.43 4,373,742.65 2. a. Extra Work 164,793.88 53,817.19 b. Adustment Comp. 232,619.04 0.00 3. Materials on Hand 130,775.00 -250,138.00 4. Earned Subject to Retention 19,833,441.35 4,177,421.84 5. Mobilization 5,112,900.00 0.00 6. Total Work Completed 24,815,566.35 7. Deductions -359,000.00 -357,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,587,341.35 3,820,421.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,820,421.84