Dept. of Trans. PROGRESS Serial No. Contract No. 18-330-15-18 02-4G5504 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 42% Location: Federal Project: 02-SIS-5-2.7/R11.4 ACIM-005-9(177) Progress payment No. 006 Payment period ending: 11-20-18 J F SHEA CONSTRUCTION INC PO BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,938,983.13 1,633,729.70 2. a. Extra Work 851,288.67 686,494.79 b. Adustment Comp. 786,549.28 553,930.24 3. Materials on Hand 117,975.00 -12,800.00 4. Earned Subject to Retention 22,694,796.08 2,861,354.73 5. Mobilization 5,112,900.00 0.00 6. Total Work Completed 27,689,721.08 7. Deductions -356,000.00 3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,451,696.08 2,864,354.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,864,354.73