Dept. of Trans. PROGRESS Serial No. Contract No. 21-236-15-15 02-4G6204 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 64% Location: Federal Project: 02-TRI-299-R3.5 NONE Progress payment No. 005 Payment period ending: 08-20-21 S.T. RHOADES CONSTRUCTION INC. PO BOX 494520 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 926,820.65 209,543.25 2. a. Extra Work 18,712.75 18,712.75 b. Adustment Comp. 3. Materials on Hand 33,750.00 0.00 4. Earned Subject to Retention 979,283.40 228,256.00 5. Mobilization 6. Total Work Completed 945,533.40 7. Deductions -10,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 969,283.40 224,256.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 224,256.00