Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-012-09-43 02-4G7204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-SIS-5 NONE Progress payment No. 008 Payment period ending: 10-23-15 MYERS AND SONS CONSTRUCTION, LP 4600 NORTHGATE BLVD SUITE 100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,507,527.72 0.00 2. a. Extra Work 89,482.71 1,548.91 b. Adustment Comp. -10,750.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,586,260.43 1,548.91 5. Mobilization 142,000.00 0.00 6. Total Work Completed 1,728,260.43 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,718,260.43 11,548.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,548.91