Dept. of Trans. PROGRESS Serial No. Contract No. 24-297-11-15 02-4H0004 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 88% Location: Federal Project: 02-SIS-97-45.0/54.1 ACNH-X089(11) 02-SIS-161-0.0/0.8 Progress payment No. 003 Payment period ending: 10-20-24 ROCKY MOUNTAIN CONSTRUCTION LLC 4815 TINGLEY LN #A KLAMATH FALLS OR 97603 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,379,615.63 3,198,140.29 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -85,495.08 4. Earned Subject to Retention 7,379,615.63 3,112,645.21 5. Mobilization 1,000,000.00 50,000.00 6. Total Work Completed 8,379,615.63 7. Deductions -10,000.00 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,369,615.63 3,156,645.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,156,645.21