Dept. of Trans. PROGRESS Serial No. Contract No. 25-237-10-55 02-4H0004 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 02-SIS-97-45.0/54.1 ACNH-X089(11) 02-SIS-161-0.0/0.8 Progress payment No. 009 Payment period ending: 08-20-25 ROCKY MOUNTAIN CONSTRUCTION LLC 4815 TINGLEY LN #A KLAMATH FALLS OR 97603 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,746,268.75 239,188.90 2. a. Extra Work 149,845.89 37,322.03 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 9,896,114.64 276,510.93 5. Mobilization 1,000,000.00 0.00 6. Total Work Completed 10,896,114.64 7. Deductions -3,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,893,114.64 273,510.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 273,510.93