Dept. of Trans. PROGRESS Serial No. Contract No. 25-233-14-39 02-4H0104 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 17% Location: Federal Project: 02-PLU-70-R78.3/90.3 ACST-P070(149) Progress payment No. 003 Payment period ending: 08-20-25 HAT CREEK CONSTRUCTION & MATERIALS INC 24339 STATE HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,501,537.75 1,997,908.27 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 231,489.00 -419,778.00 4. Earned Subject to Retention 2,733,026.75 1,578,130.27 5. Mobilization 1,173,750.00 391,250.00 6. Total Work Completed 3,675,287.75 7. Deductions -30,000.00 -30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,876,776.75 1,939,380.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,939,380.27