Dept. of Trans. PROGRESS Serial No. Contract No. 24-239-14-57 02-4H0904 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 25% Location: Federal Project: 02-SHA-5716-0.0/62.5 NONE Progress payment No. 003 Payment period ending: 08-20-24 RADMAN ELECTRIC 25013 WHITMAN ST #15-S HAYWARD CA 94544 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 320,497.50 69,717.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 320,497.50 69,717.50 5. Mobilization 6. Total Work Completed 320,497.50 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 310,497.50 59,717.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 59,717.50