Dept. of Trans. PROGRESS Serial No. Contract No. 24-327-13-53 02-4H0904 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 30% Location: Federal Project: 02-SHA-5716-0.0/62.5 NONE Progress payment No. 005 Payment period ending: 11-20-24 RADMAN ELECTRIC 25013 WHITMAN ST #15-S HAYWARD CA 94544 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 375,057.50 0.00 2. a. Extra Work 57,615.38 22,215.60 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 432,672.88 22,215.60 5. Mobilization 6. Total Work Completed 432,672.88 7. Deductions -20,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 412,672.88 12,215.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,215.60