Dept. of Trans. PROGRESS Serial No. Contract No. 22-236-11-16 02-4H4404 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 16% Location: Federal Project: 02-PLU-70-0.0/29.9 ACST-ER31-T(V00) Progress payment No. 003 Payment period ending: 08-20-22 Q & D CONSTRUCTION INC 1050 S 21ST ST SPARKS NV 89431 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,152,403.55 959,556.45 2. a. Extra Work 7,858.91 0.00 b. Adustment Comp. 3. Materials on Hand 172,994.00 -53,030.70 4. Earned Subject to Retention 1,333,256.46 906,525.75 5. Mobilization 835,523.12 835,523.12 6. Total Work Completed 1,995,785.58 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,168,779.58 1,742,048.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,742,048.87