Dept. of Trans. PROGRESS Serial No. Contract No. 23-230-10-13 02-4H4404 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 78% Location: Federal Project: 02-PLU-70-0.0/29.9 ACST-ER31-T(V00) Progress payment No. 016 Payment period ending: 08-20-23 Q & D CONSTRUCTION INC 1050 S 21ST ST SPARKS NV 89431 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,613,043.22 732,779.77 2. a. Extra Work 210,955.53 154,501.21 b. Adustment Comp. 3,919,363.88 0.00 3. Materials on Hand 4. Earned Subject to Retention 18,743,362.63 887,280.98 5. Mobilization 1,671,046.24 0.00 6. Total Work Completed 20,414,408.87 7. Deductions -6,225.60 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,408,183.27 887,280.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 887,280.98