Dept. of Trans. PROGRESS Serial No. Contract No. 24-355-12-25 02-4H7104 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 11% Location: Federal Project: 02-TEH-36-41.9/42.6 NONE Progress payment No. 002 Payment period ending: 12-20-24 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 147,754.56 144,754.56 2. a. Extra Work 226,741.44 226,741.44 b. Adustment Comp. 3. Materials on Hand 274,234.79 274,234.79 4. Earned Subject to Retention 648,730.79 645,730.79 5. Mobilization 275,500.00 275,500.00 6. Total Work Completed 649,996.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 924,230.79 921,230.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 921,230.79