Dept. of Trans. SEMI-FINAL Serial No. Contract No. 24-340-13-36 02-4J8304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-MOD-395-34.0/39.9 NONE Progress payment No. 003 Payment period ending: 10-15-24 HAT CREEK CONSTRUCTION & MATERIALS INC 24339 STATE HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,548,187.40 63,964.20 2. a. Extra Work b. Adustment Comp. -27,639.69 52,261.88 3. Materials on Hand 4. Earned Subject to Retention 1,520,547.71 116,226.08 5. Mobilization 6. Total Work Completed 1,520,547.71 7. Deductions -20,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,500,547.71 126,226.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 126,226.08