Dept. of Trans. PROGRESS Serial No. Contract No. 06-054-14-54 03-0A29U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 90% 03-YUB-5715 Federal Project: NONE Progress payment No. 14 Payment period ending: 02-17-06 ALLEN L BENDER INC 2798 INDUSTRIAL BLVD WEST SACRAMENTO CA 95691 Escrow No. 02192 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,736,327.67 716,721.76 2.a. Extra Work 683,592.77 186,604.82 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 10,419,920.44 903,326.58 5. Mobilization 6. Total Work Completed 10,419,920.44 7. Deductions -7,000.00 0.00 8. a.Contract Retentions -520,996.02 -45,166.33 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,891,924.42 858,160.25 10. Reduction Amt to Escrow 11. Payment to Escrow 250,000.00 12. Net Pymt. this Estimate 858,160.25