Dept. of Trans. PROGRESS Serial No. Contract No. 07-081-11-26 03-0A4104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 10% 03-PLA-49-3.2/7.4 Federal Project: NONE Progress payment No. 01 Payment period ending: 03-20-07 NEHEMIAH CONSTRUCTION INC 4790 E 2ND STREET BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 97,628.00 97,628.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 38,608.35 38,608.35 4. Earned Subject to Retention 136,236.35 136,236.35 5. Mobilization 6. Total Work Completed 97,628.00 7. Deductions -46,540.08 -46,540.08 8. a.Contract Retentions -13,623.64 -13,623.64 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 76,072.63 76,072.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 76,072.63