Dept. of Trans. PROGRESS Serial No. Contract No. 07-143-10-06 03-0A4104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 44% 03-PLA-49-3.2/7.4 Federal Project: NONE Progress payment No. 03 Payment period ending: 05-18-07 NEHEMIAH CONSTRUCTION INC 4790 E 2ND STREET BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 619,784.94 306,051.84 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 50,116.90 -3,351.07 4. Earned Subject to Retention 669,901.84 302,700.77 5. Mobilization 337,500.00 112,500.00 6. Total Work Completed 957,284.94 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -66,990.18 -30,270.07 b. Unsatisfactory Prog. -0.01 -0.01 c. Reduction after 95% Comp. 9. Total pay to Contractor 930,411.65 384,930.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 384,930.69