Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-042-15-48 03-0A4104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-PLA-49-3.2/7.4 Federal Project: NONE Progress payment No. 26 Payment period ending: 11-18-08 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET, STE. G BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,798,040.90 25,230.50 2.a. Extra Work 1,069,373.32 100,236.89 b. Adjustment Comp. 205,751.88 -7,259.39 3. Materials on Hand 4. Earned Subject to Retention 7,073,166.10 118,208.00 5. Mobilization 450,000.00 0.00 6. Total Work Completed 7,523,166.10 7. Deductions -259,610.21 -51,610.21 8. a.Contract Retentions -346,643.85 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 346,643.85 0.00 9. Total pay to Contractor 7,263,555.89 66,597.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 66,597.79