Dept. of Trans. PROGRESS Serial No. Contract No. 21-117-09-41 03-0A5704 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 46% Location: Federal Project: 03-YUB-20-13.3/18.2 ACNH-P020(191) Progress payment No. 014 Payment period ending: 04-20-21 TEICHERT CONSTRUCTION PO BOX 13557 SACRAMENTO CA 95853 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,642,849.21 564,050.92 2. a. Extra Work 498,649.37 0.00 b. Adustment Comp. 438,756.96 384,233.36 3. Materials on Hand 60,356.70 10,219.00 4. Earned Subject to Retention 22,640,612.24 958,503.28 5. Mobilization 3,557,848.19 0.00 6. Total Work Completed 26,138,103.73 7. Deductions -7,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,191,460.43 957,503.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 957,503.28