Dept. of Trans. PROGRESS Serial No. Contract No. 05-054-16-54 03-0A6004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 21% 03-PLA-80-14.3/33.3 Federal Project: ACIM-080-3(231) ACIM-080-3(231) ACBH-080-E(231) Progress payment No. 08 Payment period ending: 02-18-05 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 958276830 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,836,449.01 399,261.00 2.a. Extra Work 24,648.39 3,850.00 b. Adjustment Comp. 136,354.14 -3,256.60 3. Materials on Hand 243,249.78 0.00 4. Earned Subject to Retention 4,240,701.32 399,854.40 5. Mobilization 1,650,000.00 550,000.00 6. Total Work Completed 5,647,451.54 7. Deductions -77,009.46 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,813,691.86 948,854.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 948,854.40