Dept. of Trans. PROGRESS Serial No. Contract No. 05-327-10-00 03-0A6004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 59% 03-PLA-80-14.3/33.3 Federal Project: ACIM-080-3(231) ACIM-080-3(231) ACBH-080-E(231) Progress payment No. 19 Payment period ending: 11-18-05 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 958276830 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,736,253.77 1,169,549.40 2.a. Extra Work 150,749.51 5,535.91 b. Adjustment Comp. 4,731,652.03 339,092.13 3. Materials on Hand 243,249.78 -39,867.25 4. Earned Subject to Retention 23,861,905.09 1,474,310.19 5. Mobilization 2,200,000.00 0.00 6. Total Work Completed 25,818,655.31 7. Deductions -369,396.81 -270,387.35 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,692,508.28 1,203,922.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,203,922.84