Dept. of Trans. PROGRESS Serial No. Contract No. 10-201-18-51 03-0A6314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 52% 03-NEV-80-R9.2/13.6 Federal Project: ACIM-080-4(184) Progress payment No. 29 Payment period ending: 07-20-10 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 958276830 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 35,859,844.42 2,251,287.27 2.a. Extra Work 482,219.19 70,689.80 b. Adjustment Comp. 1,019,888.40 -29,778.28 3. Materials on Hand 4. Earned Subject to Retention 37,361,952.01 2,292,198.79 5. Mobilization 5,640,000.00 0.00 6. Total Work Completed 43,001,952.01 7. Deductions -26,800.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 42,975,152.01 2,282,198.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,282,198.79