Dept. of Trans. PROGRESS Serial No. Contract No. 10-235-14-52 03-0A6314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 57% 03-NEV-80-R9.2/13.6 Federal Project: ACIM-080-4(184) Progress payment No. 30 Payment period ending: 08-20-10 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 958276830 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,403,806.37 4,543,961.95 2.a. Extra Work 543,892.36 61,673.17 b. Adjustment Comp. 1,015,134.28 -4,754.12 3. Materials on Hand 4. Earned Subject to Retention 41,962,833.01 4,600,881.00 5. Mobilization 5,640,000.00 0.00 6. Total Work Completed 47,602,833.01 7. Deductions -36,800.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 47,566,033.01 4,590,881.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,590,881.00