Dept. of Trans. PROGRESS Serial No. Contract No. 10-323-11-28 03-0A6314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 67% 03-NEV-80-R9.2/13.6 Federal Project: ACIM-080-4(184) Progress payment No. 34 Payment period ending: 11-19-10 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 958276830 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 48,789,931.93 1,939,543.87 2.a. Extra Work 837,117.26 133,552.58 b. Adjustment Comp. 1,141,097.27 -1,888.82 3. Materials on Hand 4. Earned Subject to Retention 50,768,146.46 2,071,207.63 5. Mobilization 5,640,000.00 0.00 6. Total Work Completed 56,408,146.46 7. Deductions -66,800.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 56,341,346.46 2,061,207.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,061,207.63