Dept. of Trans. PROGRESS Serial No. Contract No. 11-053-13-22 03-0A6314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 65% 03-NEV-80-R9.2/13.6 Federal Project: ACIM-080-4(184) Progress payment No. 38 Payment period ending: 02-18-11 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 958276830 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 49,699,304.32 0.00 2.a. Extra Work 969,298.24 100,390.15 b. Adjustment Comp. 1,064,867.72 -76,229.55 3. Materials on Hand 4. Earned Subject to Retention 51,733,470.28 24,160.60 5. Mobilization 5,640,000.00 0.00 6. Total Work Completed 57,373,470.28 7. Deductions -77,800.00 -17,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 57,295,670.28 7,160.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,160.60