Dept. of Trans. PROGRESS Serial No. Contract No. 07-232-16-44 03-0A6324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 14% 03-NEV-80-R2.5/R5.6 Federal Project: ACIM-080-4(180) Progress payment No. 04 Payment period ending: 08-20-07 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 958276830 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,259,967.01 3,018,998.23 2.a. Extra Work 39,384.00 15,355.31 b. Adjustment Comp. 3. Materials on Hand 102,663.42 101,622.42 4. Earned Subject to Retention 8,402,014.43 3,135,975.96 5. Mobilization 531,375.00 177,125.00 6. Total Work Completed 8,830,726.01 7. Deductions -38,020.00 -20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,895,369.43 3,293,100.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,293,100.96