Dept. of Trans. PROGRESS Serial No. Contract No. 08-267-18-17 03-0A6324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 31% 03-NEV-80-R2.5/R5.6 Federal Project: ACIM-080-4(180) Progress payment No. 19 Payment period ending: 09-20-08 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 958276830 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,879,600.58 3,487,178.89 2.a. Extra Work 687,960.52 8,568.02 b. Adjustment Comp. 158,795.48 0.00 3. Materials on Hand 57,006.16 0.00 4. Earned Subject to Retention 42,783,362.74 3,495,746.91 5. Mobilization 708,500.00 0.00 6. Total Work Completed 43,434,856.58 7. Deductions -30,340.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 43,461,522.74 3,485,746.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,485,746.91