Dept. of Trans. PROGRESS Serial No. Contract No. 12-115-12-04 03-0A6324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 03-NEV-80-R2.5/R5.6 Federal Project: ACIM-080-4(180) Progress payment No. 58 Payment period ending: 04-19-12 TEICHERT CONSTRUCTION 4401 DULUTH AVENUE ROSEVILLE, CA 95678 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 64,870,830.89 0.00 2.a. Extra Work 2,123,700.79 8,459.04 b. Adjustment Comp. 990,675.64 0.00 3. Materials on Hand 4. Earned Subject to Retention 67,985,207.32 8,459.04 5. Mobilization 708,500.00 0.00 6. Total Work Completed 68,693,707.32 7. Deductions -3,340.00 7,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 68,690,367.32 15,459.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,459.04