Dept. of Trans. PROGRESS Serial No. Contract No. 10-021-14-43 03-0A6334 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 53% 03-NEV-80-R5.2/R13.3 Federal Project: NONE Progress payment No. 13 Payment period ending: 01-20-10 R AND L BROSAMER INC 1777 OAKLAND BLVD SUITE 300 WALNUT CREEK CA 94596 Escrow No. 02403 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,512,723.37 0.00 2.a. Extra Work 492,129.14 53,099.56 b. Adjustment Comp. 354,427.25 10,050.00 3. Materials on Hand 1,369,075.76 0.00 4. Earned Subject to Retention 21,728,355.52 63,149.56 5. Mobilization 5,361,800.00 0.00 6. Total Work Completed 25,721,079.76 7. Deductions -20,054.24 -10,000.00 8. a.Contract Retentions -1,086,417.78 -3,157.48 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,983,683.50 49,992.08 10. Reduction Amt to Escrow 11. Payment to Escrow 1,086,410.00 12. Net Pymt. this Estimate 49,992.08