Dept. of Trans. FINAL Serial No. Contract No. 09-299-13-45 03-0A7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-YUB-70-16.4/25.8 Federal Project: ACNH-P070(95) Progress payment No. 05 Payment period ending: 07-23-09 TEICHERT CONSTRUCTION P O BOX 700 LINCOLN CA 956480700 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,630,829.92 0.00 2.a. Extra Work 24,007.38 0.00 b. Adjustment Comp. -346,207.06 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,308,630.24 0.00 5. Mobilization 28,821.00 0.00 6. Total Work Completed 3,337,451.24 7. Deductions -720.00 25,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,336,731.24 25,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,000.00