Dept. of Trans. PROGRESS Serial No. Contract No. 01-201-13-51 03-0A7814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 33% 03-SAC-99-17.6/21.6 Federal Project: ACNH-P099(400) Progress payment No. 04 Payment period ending: 07-20-01 TEICHERT CONSTRUCTION P O BOX 15144 SACRAMENTO CA 95851 Escrow No. 01613 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,840,006.80 577,967.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,840,006.80 577,967.80 5. Mobilization 412,300.00 0.00 6. Total Work Completed 3,252,306.80 7. Deductions 8. a.Contract Retentions -190,840.65 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,061,466.15 577,967.80 10. Reduction Amt to Escrow 11. Payment to Escrow 190,840.00 12. Net Pymt. this Estimate 577,967.80