Dept. of Trans. PROGRESS Serial No. Contract No. 02-203-12-15 03-0A7814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 94% 03-SAC-99-17.6/21.6 Federal Project: ACNH-P099(400) Progress payment No. 16 Payment period ending: 07-19-02 TEICHERT CONSTRUCTION P O BOX 15144 SACRAMENTO CA 95851 Escrow No. 01613 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,817,918.00 928,405.50 2.a. Extra Work 26,332.18 0.00 b. Adjustment Comp. 565,512.63 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,409,762.81 928,405.50 5. Mobilization 434,000.00 0.00 6. Total Work Completed 10,843,762.81 7. Deductions 8. a.Contract Retentions -520,488.14 -46,420.27 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,323,274.67 881,985.23 10. Reduction Amt to Escrow 11. Payment to Escrow 450,000.00 12. Net Pymt. this Estimate 881,985.23