Dept. of Trans. SEMI-FINAL Serial No. Contract No. 05-088-14-39 03-0A7814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-99-17.6/21.6 Federal Project: ACNH-P099(400) Progress payment No. 24 Payment period ending: 12-11-02 TEICHERT CONSTRUCTION P O BOX 15144 SACRAMENTO CA 95851 Escrow No. 01613 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,121,173.68 -62,373.20 2.a. Extra Work 367,609.77 160,112.70 b. Adjustment Comp. 1,174,067.26 -76,051.31 3. Materials on Hand 4. Earned Subject to Retention 11,662,850.71 21,688.19 5. Mobilization 434,000.00 0.00 6. Total Work Completed 12,096,850.71 7. Deductions -12,500.00 0.00 8. a.Contract Retentions -550,615.65 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 550,615.65 0.00 9. Total pay to Contractor 12,084,350.71 21,688.19 10. Reduction Amt to Escrow -450,000.00 0.00 11. Payment to Escrow 450,000.00 12. Net Pymt. this Estimate 21,688.19