Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 01-270-13-50 03-0A9404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-99-0.1/9.4 Federal Project: DBNH-P099(383) Progress payment No. 13 Payment period ending: 02-16-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01280 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,796,601.75 0.00 2.a. Extra Work 192,384.85 128,123.26 b. Adjustment Comp. 65,322.35 -45,740.58 3. Materials on Hand 4. Earned Subject to Retention 3,054,308.95 82,382.68 5. Mobilization 6. Total Work Completed 3,054,308.95 7. Deductions 8. a.Contract Retentions -148,596.31 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 148,596.31 148,596.31 9. Total pay to Contractor 3,054,308.95 230,978.99 10. Reduction Amt to Escrow -148,590.00 -148,590.00 11. Payment to Escrow 148,590.00 12. Net Pymt. this Estimate 82,388.99