Dept. of Trans. FINAL Serial No. Contract No. 11-312-18-02 03-0C0004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-99-19.4/19.8 Federal Project: NONE Progress payment No. 51 Payment period ending: 10-13-11 PARKER LANDSCAPE DEVELOPMENT INC 6251 SKY CREEK DR SUITE A SACRAMENTO CA 95828 Escrow No. 02351 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,291,004.39 0.00 2.a. Extra Work 105,798.10 0.00 b. Adjustment Comp. 1,400.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,398,202.49 0.00 5. Mobilization 26,466.38 0.00 6. Total Work Completed 1,424,668.87 7. Deductions 8. a.Contract Retentions -73,127.76 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 73,127.76 0.00 9. Total pay to Contractor 1,424,668.87 0.00 10. Reduction Amt to Escrow -73,000.00 0.00 11. Payment to Escrow 73,000.00 12. Net Pymt. this Estimate 0.00