Dept. of Trans. PROGRESS Serial No. Contract No. 19-266-08-59 03-0C4724 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 79% Location: Federal Project: 03-YOL-16-20.5/31.6 HSST-P016(41) Progress payment No. 013 Payment period ending: 09-20-19 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,473,487.52 1,417,866.63 2. a. Extra Work 459,531.78 71,596.67 b. Adustment Comp. 15,268.62 0.00 3. Materials on Hand 11,615.18 0.00 4. Earned Subject to Retention 8,959,903.10 1,489,463.30 5. Mobilization 1,410,000.00 70,500.00 6. Total Work Completed 10,358,287.92 7. Deductions -21,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,348,903.10 1,539,963.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,539,963.30