Dept. of Trans. PROGRESS Serial No. Contract No. 09-142-07-05 03-0C7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 58% 03-PLA-80-R66.3/68.5 Federal Project: ACIM-080-4(182) Progress payment No. 14 Payment period ending: 05-20-09 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,436,874.29 1,946,455.31 2.a. Extra Work 256,226.08 3,843.70 b. Adjustment Comp. 163,229.65 -60,882.63 3. Materials on Hand 4. Earned Subject to Retention 14,856,330.02 1,889,416.38 5. Mobilization 2,400,000.00 0.00 6. Total Work Completed 17,256,330.02 7. Deductions -15,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,241,330.02 1,889,416.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,889,416.38