Dept. of Trans. PROGRESS Serial No. Contract No. Dept. of Trans. PROGRESS Serial No. Contract No. 05-202-13-39 10-0K0004 05-207-11-59 03-0E1604 PROGRESS PAYMENT VOUCHER %complete: %time: PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 15% Location: 31% 38% 10-SJ-5-26.3/29.4 Federal Project: 03-SAC-5-1.0/26.9 Federal Project: NONE NONE Progress payment No. 01 Payment period ending: 07-20-05 Progress payment No. 01 Payment period ending: 07-20-05 CALIFORNIA ENGINEERING CONTRACTORS CHEMICAL INC CONTRACTORS INC 3130 DEPOT ROAD 20 HAPPY VALLEY ROAD HAYWARD CA 94545 PLEASANTON CA 94566 Escrow No. 00000 Escrow No. 00000 Total Estimate This Estimate Total Estimate This Estimate 1. Contract Itms Without Mobil. 57,010.00 57,010.00 1. Contract Itms Without Mobil. 99,315.20 99,315.20 2.a. Extra Work 2.a. Extra Work b. Adjustment Comp. b. Adjustment Comp. 3. Materials on Hand 3. Materials on Hand 4. Earned Subject to Retention 99,315.20 99,315.20 4. Earned Subject to Retention 57,010.00 57,010.00 5. Mobilization 5. Mobilization 6. Total Work Completed 99,315.20 6. Total Work Completed 57,010.00 7. Deductions -250.00 -250.00 7. Deductions 8. a.Contract Retentions -5,701.00 -5,701.00 8. a.Contract Retentions -6,503.39 -6,503.39 b. Unsatisfactory Prog. b. Unsatisfactory Prog. c. Reduction after 95% Comp. c. Reduction after 95% Comp. 9. Total pay to Contractor 51,059.00 51,059.00 9. Total pay to Contractor 92,811.81 92,811.81 10. Reduction Amt to Escrow 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 51,059.00 12. Net Pymt. this Estimate 92,811.81