Dept. of Trans. PROGRESS Serial No. Contract No. 07-173-10-18 03-0E1704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 90% 03-SAC-80-M1.4/14.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-21-07 CONTRACTORS CHEMICAL INC 3130 DEPOT ROAD HAYWARD CA 94545 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 333,111.00 122,518.00 2.a. Extra Work 55,630.63 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 388,741.63 122,518.00 5. Mobilization 55,000.00 2,750.00 6. Total Work Completed 443,741.63 7. Deductions -6,000.00 0.00 8. a.Contract Retentions -19,437.08 -5,500.97 b. Unsatisfactory Prog. -6,125.90 -6,125.90 c. Reduction after 95% Comp. 9. Total pay to Contractor 412,178.65 113,641.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 113,641.13