Dept. of Trans. PROGRESS Serial No. Contract No. 07-080-15-01 03-0E1804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 60% 03-SAC-50-L1.1/R2.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 03-20-07 BAY LINE CUTTING AND CORING INC 1033 YERBA BUENA AVE OAKLAND CA 94608 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 254,179.00 64,090.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 254,179.00 64,090.00 5. Mobilization 47,500.00 0.00 6. Total Work Completed 301,679.00 7. Deductions -2,000.77 -2,000.77 8. a.Contract Retentions -12,708.95 -3,204.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 286,969.28 58,884.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,884.73