Dept. of Trans. PROGRESS Serial No. Contract No. 08-235-14-58 03-0E2004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 42% 03-SIE-49-2.3/R3.7 Federal Project: OTS-05(18) Progress payment No. 02 Payment period ending: 08-20-08 R N R CONSTRUCTION INC 8 LIGHT SKY COURT SACRAMENTO CA 95828 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 689,328.75 433,017.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 689,328.75 433,017.50 5. Mobilization 98,000.00 4,900.00 6. Total Work Completed 787,328.75 7. Deductions -65,318.00 -55,318.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 722,010.75 382,599.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 382,599.50