Dept. of Trans. PROGRESS Serial No. Contract No. 06-234-13-17 03-0E3204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 25% 98% 03-COL-5-R1.9/R8.2 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-18-06 CONSTRUCTION FUNDS CONTROL SERVICES TRUSTEE FOR PROFESSIONAL CONSTRUCTION SERVICES 1330 ARNOLD DRIVE, STE 242 MARTINEZ, CA 94553Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 161,846.00 161,846.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 161,846.00 161,846.00 5. Mobilization 9,500.00 9,500.00 6. Total Work Completed 171,346.00 7. Deductions 8. a.Contract Retentions -13,778.50 -13,778.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 157,567.50 157,567.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 157,567.50