Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-312-16-35 03-0E3404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-COL-5-R19.1/R22.5 Federal Project: NONE Progress payment No. 04 Payment period ending: 08-13-07 BALDWIN CONTRACTING COMPANY INC 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 649,059.48 -1,565.00 2.a. Extra Work 170,208.39 53,529.92 b. Adjustment Comp. 63,186.91 -15,743.34 3. Materials on Hand 4. Earned Subject to Retention 882,454.78 36,221.58 5. Mobilization 22,500.00 0.00 6. Total Work Completed 904,954.78 7. Deductions -13,000.00 10,000.00 8. a.Contract Retentions -31,071.84 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 31,071.84 0.00 9. Total pay to Contractor 891,954.78 46,221.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 46,221.58